How much of a project budget should go to MEAL?

A common rule of thumb is 5 to 10 percent of project cost for MEAL. See what to include, when to go higher or lower, and how to check your own budget.

Short answer

Many agencies use 5 to 10 percent of the total project budget for monitoring, evaluation, accountability and learning (MEAL) as a starting range. Go higher for baselines, endline surveys, independent evaluations or new feedback tools. Go lower for very large budgets. Add up every MEAL cost, including part of staff salaries, and check the total against your logframe, not only against a percentage.

Key points

  • 5 to 10 percent of project cost is a common starting range, not a rule.
  • Count all MEAL costs: staff time, surveys, field visits, tools, feedback channels and evaluations.
  • Indicators drive cost. Outcome indicators need surveys and cost more than output counts.
  • Very large budgets can need a lower percentage. Short projects may need less.
  • If the budget cannot cover the MEAL plan, cut the plan, not the quality.

Why is MEAL budgeting often too low?

MEAL is easy to cut. A budget is too high by 8 percent, and the baseline survey looks like the item nobody will miss. Six months later, the team cannot show change, and the donor asks for numbers that do not exist.

MEAL means monitoring, evaluation, accountability and learning. It is how a project knows if it is on track, hears from the people it serves, and learns what to change. A MEAL budget that is too small leads to weak data, late problem detection and thin reports. The IRC MEAL Handbook says that if a budget cannot cover all planned MEAL activities, the gaps should be raised with the project lead and the MEAL approach should be revised. That is the right order: be honest about the gap, then adjust the plan.

What percentage of a project budget is normal?

There is no single legal or global figure. Several agencies use a range of about 5 to 10 percent as a guide.

  • The Mercy Corps design, monitoring and evaluation guidance describes a rule of thumb of 5 to 10 percent of project budgets, and notes that donor guidance varies within that range.
  • The IRC MEAL Handbook says a country can estimate MEAL at about 5 to 10 percent of total project cost, and that the cost rises with new feedback technology, baseline and endline surveys or independent evaluations.
  • The Global Fund guidance for health grants also recommends 5 to 10 percent for M&E.

Treat this as a check, not a target. Your donor agreement, your indicators and your context decide the real number. Donor rules differ, so check your own agreement or ask a qualified adviser.

What should you count as MEAL cost?

Add up every cost that supports MEAL, even when it sits inside another line, such as a part-time officer's salary.

MEAL costExamples
StaffMEAL officer, enumerators, a share of programme staff time
TrainingData collection training, tool testing, partner orientation
Data collectionBaseline, endline, post-distribution monitoring, phone credit, transport
SystemsPhones or tablets, KoboToolbox licences or servers, database setup
AccountabilityHotline or suggestion boxes, community meetings to share results
LearningReview workshops, lessons learned sessions, report printing
EvaluationMid-term or final evaluation, consultant fees, translation

If you use KoboToolbox, the EMPO KoboToolbox XLS forms package can lower form design time.

How do you build a MEAL budget in five steps?

  1. List your indicators. Open the logframe. For each indicator, write how you will measure it and how often.
  2. Mark the expensive ones. Outcome indicators, such as changes in behaviour or conditions, usually need surveys or focus groups. Output counts from attendance sheets cost little.
  3. Cost each activity. Include staff days, transport, phone credit, training and tool costs. Use real local prices.
  4. Add the shared costs. Include the share of the MEAL officer, accountability channels and learning events.
  5. Check the total. Divide total MEAL cost by total project cost. If it is far below 5 percent, check that you have not left out a baseline, an evaluation or the accountability system.

When should the percentage go up or down?

Mercy Corps guidance gives clear examples. Pilot projects and high-profile projects may need more than the usual range. A very large programme may need less in percentage terms, because some MEAL costs do not grow in line with the budget. The same guidance says very short projects, of nine to twelve months or less, may only be able to measure outputs, so they may not need the full amount.

In Myanmar, other factors apply. Remote data collection by phone can save travel cost but takes more staff time and may reduce sample quality. Limited access may mean you need local monitors and extra verification steps. Burmese and English forms, and translation of findings, add cost. Build these into the budget at the proposal stage rather than asking for changes later.

What if the donor will not fund enough MEAL?

First, ask. Many donors accept a clear explanation. Show the MEAL plan and what each activity costs.

If the money is fixed, reduce the plan, not the quality of the plan. Fewer indicators, a smaller sample or one evaluation instead of two are honest choices. Weak data on many indicators is worse than good data on a few. Record the decision in the MEAL plan so the donor and your team know what is covered. Our guide to a proposal budget narrative shows how to explain MEAL costs line by line, and simple MEAL dashboards shows how to use the data you collect.

How EMPO can help

EMPO is a trusted, Yangon-based training and consultancy provider and one of Myanmar's leading names in practical NGO training, with 1,200+ people trained and 15 partner organisations. We run MEAL and intensive support training, and help organisations design MEAL systems, online or in person across Myanmar, in English and Burmese. See our services or contact us.

Sources

Questions people ask

Can we put MEAL costs inside other budget lines?

Yes, if the donor template has no MEAL line. Name the item clearly, for example "MEAL training for project staff", so the donor can see the total MEAL investment.

Who pays for an external evaluation?

It depends on the donor. Some donors commission and pay for evaluations themselves. Others expect the project budget to cover them. Ask early and write the answer into your budget notes.

What if the donor sets a low overhead and no MEAL line?

Raise it before you submit. Show the donor what the MEAL plan needs, and offer a smaller plan if the money is fixed.